Before creating maintenance schedules on your equipment, you should create a list of the tasks to be performed on those assets. In the eMaint system, these tasks are called PMTasks. A PM Task can be assigned to multiple PM Schedules, which will allow you to manage task changes very easily by editing the PM Task, then publishing it to all associated PM Schedules.
The PMTasks link is located on the left hand side of the screen as its own table named Tasks (if not there, it can be added). From the list view, you can add new tasks by clicking the big plus button at the top of the list or you can access one of the existing records for viewing or editing by clicking on the task number of the selected PM task.

IMPORTANTNOTE:
BEFORE START BUILDING YOUR TASK LIBRARY YOU NEED TO UNDERSTAND THE 2 DIFFERENT METHODS THAT YOU WILL HAVE AVAILABLE TO CHOOSE FROM. ONCE YOU UNDERSTAND THE BENEFITS OF BOTH OPTIONS, YOU SHOULD DECIDE WHAT METHOD TO GO WITH.
METHOD 1 - Create a Task Procedure and write (or paste) all the procedures into a single field in the Task form (Detailed Description).
Advantages: It’s faster method to build a task library. You can quickly create these tasks manually (or through Data Import) since you can copy procedures from existing documents that you may have and paste them into a single Multi Text field.
Disadvantages: If you are planning on putting a check mark or writing comments when completing each procedure (using a computer or mobile device), it will be very time consuming to edit the “Detailed Description” and find the end of each procedure to write notes there.
The PM Task Detail Screen is a very small form, making tasks easy to add. To create a task using this first method you will need to populate the fields below:
TaskNo. - This field is the unique identifier for the task.
BriefDescription - This field is for defining the task.
DetailedDescription - This field is an unlimited text field that can contain as much information as you wish. You can either write the procedures here or you can paste them from any existing document you may have
Make sure to click “Save New Record” when you are done.
Before

After

AddingTaskstoPMSchedules (METHOD 1)
After creating a task you will be able to select it when setting up a PM schedule. On the PM schedule form there’s a field called “Task No” that when clicked will give you a popup window displaying all the tasks previously saved in your task library.

After selecting the desired task, the “Brief Description” and the “Detailed Description” fields will be automatically populated with the information contained in the task.

EditingPMTasks
When a task change, it would be time consuming if you had to navigate to each PM Schedule and make the necessary adjustments. The PM Tasks make this process much easier by allowing you to adjust the PM Task, then publish those adjustments to each associated PM Schedule.

Click the Publish link located under the Actions menu on command bar.
You will be presented with the task so you may review it one last time before publishing. When you are ready, click the Proceed button.


NOTE: Upon completion, you will be presented with a list of Assets that were updated with the task changes.
METHOD 2 - Create the Task then add the procedures separately in the “Task Procedures” related table.
Advantages: Choosing this method will allow you to easily add comments, mark procedures as completed, pass or fail each WO procedure (if your account is configured with these options), etc. In addition, if you are using a mobile device it will be very simple to go through the WO procedures making sure that you are quickly recording everything that needs to be recorded for each procedure. Also, there are configurations available that will add extra functionality to the WO Procedures table. A good example of that is a configuration that will automatically create a WO for failed procedures (Ifyouwanttolearnmoreaboutthistypeofconfiguration, pleasecontacttheeMaintServicesTeam).
Disadvantages: It’s a little bit more time consuming to create or import procedures using this method. However, once everything is in the system, it will not only be easier to manage the procedures in Work Orders, but as mentioned before, it will also offer you more configuration options than the first Method.
On the PM Tasks table there’s a related table called TaskProcedures. These are the procedures that you would attach to a PM when you want to store each procedure as an individual record.

To use this method you first need to create a task. This time you are NOT going to add all the procedures in the “Detailed Description” field. You can use this field to give general instructions about the procedures.

After saving the Task, you will need to click on the “Related Tables” tab where you will see the “Task Procedures” related table. In that section, click the “Add New Record” button and start creating the tasks separately, one at the time (this can also be done using the data import tool).

IMPORTANTNOTE:
Ifyoudon’tseethe “TaskProcedures” whenaccessingtheRelatedTablesit’sbecauseit’snotondisplay. Todisplaythistable, hoverover “Options”, clickon “ManageRelatedTables”, thenmakesureTaskProceduresisbelowtheDisplaysection. 
|
When you are done adding all the procedures, your task will look similar to the one demonstrated below:

AddingTaskstoPMSchedules (METHOD 2)
Now you will be able to associate this task with any PM schedule. On the PM schedule form, select the desired task into the “Task No” field. This process is very similar to the one demonstrated for the first method. The only difference is that after selecting the Task Number on the PM Schedule form, you will need to publish the task in order for its “Task Procedures” to carry over to the “PM Procedures” related table within the PM Schedule table.

After associating the task with a PM schedule, return to the “Task Library” and publish that task.

After publishing that task, the procedures will appear on the “PM Procedures” related table.

NOTE: Every time this PM generates a WO these procedures will also appear in the “Work Procedures” section within the Work Order table.

5 - PMSettings
The PM settings can only be modified by the administrator. They allow you to activate automatic generation and emailing of the PM schedules in your system. There are two ways to access PM settings. This can be accomplished through “Account Settings” on the top left where the company name dropdown is located, or by clicking on the employee name and picking “Account Settings” from this area.

EnableDailyPMGeneration & Email - Turning this option on allows automatic PM generation to occur within the account.
FileType- This allows the user to choose the file type that is attached to a PM email.
ProducePM’sautomaticallyeverydayat- This is the time chosen by the user for the PM to auto generate on a daily basis..
SendemailwhennoPM’saregenerated - Sends an email when no PM is generated for the day.
SendPMSummaryandworkorderstoAdministrator - Sends PM summary and work orders to the administrator.
SendPMworkorderstothePerformFor - Sends PM work order email to the perform for person.
SendPMworkorderstotheAssignto - Sends PM work order email to the assign to person.
SendPMSummaryandworkorderstoOtherAddress - Sends PM summary and work order to the email addresses specified in the field.
SendPMSummaryandworkorderstoPMField -
AutomaticallygeneratePMonexceededmeterreading - Allows meter based PMs to generate when meters exceed their limit.
PreventCalendarBasedPMsectiononcloseout - Prevents adding PM information on closeout for calendar based PMs.
EnableUpdateStandardTimeforallcontactcategories - Enables update standard time for all contact categories.
This session will delve further into the PM module including the generation of PMs (manual and automatic), building a task library, Managing existing PMs and copying PMs from one asset to many others.